The project includes the extension of Container Terminal 2 at Jebel Ali Port. Works will provide additional berth for vessels and will increase the capacity of Terminal by about 1 million TEUs.

The main items of work comprise:
Construction of 400m long concrete block quay wall along with associated dredging and marine accessories.
Reclamation of container terminal together with the associated paving works.
Installation of crane rails together with foundation works.
Utilities and services include potable and storm water services, street lighting, civil works for HV, LV and telecommunication systems.

Major quantities:
Earthworks / filling: 763,785 m3
Dredging: 118,000 m3
Concrete: 135,020 m3
Reinforcement: 2,105 ton
Concrete block paving: 120,335 m2
Bored piling for crane rails: (dia. 1,000mm x 20m deep): 124 nos. (dia. 600mm x 17m deep): 502 nos.

Categories : Marine & Offshore