The project incldued the construction of the Refinery’s Main Control Building, Seven Electrical Substations (no. 01, 11, 12, 16, 1603, 1107 & 1209), Process Interface Building and Operator Shelter, with a total area of 17,000 m2
The main items of work comprised:
Earthworks, Concrete Works and Finishings for Buildings.
Plumbing and Sanitary Networks.
Detailed Engineering and Installation of Power and Lighting System.
Detailed Engineering and Installation of Grounding and Lightning Protection.
Detailed Engineering and Installation of HVAC System.
Detailed Engineering and Installation of Fire & Gas detection and Protection Systems.
Telephone / LAN / Badge Reading Cabling Systems.
Pre-commissioning and Start-up of all the systems.
Major Quantities:
Excavation: 44,120 m3
Backfilling: 38,650 m3
Concrete: 21,000 m3
Reinforcement: 4,3200 T
Communication and calling system: 83,396 LM