The works include the civil and structural components associated with the buildings and the site infrastructure including the underground services and mechanical and electrical installations.The civil and building works are associated with Phase 4A and the external paving and associated underground services of the Phase 5 development of the Erhama Bin Jaber Al Jalahma Shipyard.

The main items of work comprise:
BUILDINGS:
Super Yacht Facility
Workshop
Paintshop
Energy Centre and Substations

EXTERNAL WORKS PHASE 4A
All paving
Underground surface water and foul water drainage
Drawpits and duct runs
Fencing and gates

EXTERNAL WORKS PHASE 5
All paving
Underground surface water and foul water drainage
Drawpits and duct runs
Fencing and gates
Weighbridge
Washdown area and contaminated water drainage.

Major quantities:
Concrete works: 35,000 m3 (including concrete paving)
Reinforcement: 350 ton
Blockwork walls: 16,000 m2.

Categories : Infrastructure