The project included design, fabricate, deliver, furnish, deliver to site, store, install, test, start-up, commission, maintain until Taking Over and Acceptance Certificate of: Civil works for Cairo West 2×350 MW Thermal Power Plant, Units (7) and (8).
The main items of work comprised:
Site Development and Underground Facilities
Power Generating Facilities
Auxiliary Facilities
HVAC System
Field Erected Tanks
Lift Stations
Circulating Water Pump House Overhead Bridge Crane
Fire Hydrants, Hydrant Connection Isolation Valves, and Post indicator Valves for Underground Fire Protection Service.
Communication and Paging System
Lightning Protection System and Grounding System
Cables and Raceways, and Underground Duct Bank
Lighting and Power Receptacles