Zawia Combined Cycle Power Plant Project. (Subcontract for Cooling Water Intake Pipework)

The project included cooling water intake pipework for the Zawia combined cycle power plant.

The main items of work comprised:
Dredging of seabed trench for a total length of 390 m and depositing the dredged material at one side of the trench.
Total Volume of Dredging: 148,300 m3.
Installation of four rows of 2600mm dia. GRP pipes in the seabed trench extending approx. 390 m from shoreline.
Installation of 4 nos. pre-cast concrete intake heads.
Backfilling of the trench using excavated material and armor rocks.


  • Construction From: 12/2004
    Construction To: 07/2006
    Consulting Enginner: Laymer International (of Germany)
    Contract Amount (IN "000" US$): 13,150
    Archirodon Portion: 100%
    Owner: General Electricity Company of Libya (GECOL) Main Contractor: Hyundai Engineering & Construction Co. Ltd.