Port Said East Container Terminal Project (Phase I, Stage 1)

The project included construction of Terminal in two stages. Stage 1 consists of container storage area to the North and infrastructure works to all the buildings.

The main items of work comprised:
Earth works including excavation, disposal of unsuitable material, soil replacement, and filling to bring the level up to the underside of paving construction, as required for an approx. 400,000m2 paving area with interlocking concrete paving blocks, concrete and gravel.
Infrastructure works including drainage ducts, pipe work and sub-pavement services.
Asphalt road works.
Five-story administration building, service building and other ancillary buildings.
Mechanical and electrical works.


  • Construction From: 06/2003
    Construction To: 11/2005
    Consulting Enginner: Posford Duvivier Haskoning Pacer, England
    Contract Amount (IN "000" US$): 40,372
    Archirodon Portion: 100%
    Owner: Suez Canal Container Terminal S.A.E. Cairo, Egypt