The project included procurement and construction of the expansion to the potable water production capacities at the existing r.o water treatment plant (wtp).
The main items of work comprised :
The upgrade and associated support facilities include raw water supply system, potable water distribution networks, addition of a potable water distribution network and the addition of a potable water pump at the north west station.
The expansion of the r.o. plant include the new installation of three 7,570 cubic meter per day water plants.
The expansion of the existing water treatment facilities will include a new pump station consisting of four pumps, four new raw water wells, four replacement raw water and offsite potable water and brine pipelines.
The scope of work includes all associated civil, mechanical, piping, electrical and instrumentation works.

Categories : Industrial