The project includes track laying and miscellaneous railway works for the Ras Al-Khair to Jubail Industrial City Saudi Railways Project.

The main items of work comprise:
Track installation, including laying of ballast, tamping, welding, distressing and grinding.
Turnouts installation
Installation of guard rails.
Installation of bumping posts.
Installation of Km marker points
«On the job» training of selected SBG employees.
Total length of track laying: 88 K


  • Construction From: 06/2013
    Construction To: 08/2016
    Consulting Enginner: The Louis Berger Group Inc. in J.V. with Canarail Consultants Inc. Systra S.A.and SCEC K & A
    Contract Amount (IN "000" US$): 23,200
    Archirodon Portion: 100%
    Owner: Saudi Railways Company (SAR)