The project included the design and construction of a loading / unloading facility for LNG carriers including a landing bridge, jetty head, 5 nos. mooring dolphins and 4 nos. breasting dolphins. The structures were constructed on tubular steel piles of 1220-mm dia. and 1520-mm dia, filled with reinforced concrete.

The main items of work comprised :
— access ladders
— mooring rings
— quick release hooks
— steel catwalk etc.

Categories : Industrial , Marine & Offshore